To address the client's specific challenges, Everunion's engineering team conducted a thorough assessment of the client's building conditions, workflows, and operational requirements, then designed and implemented a hybrid high-density storage system combining AS/RS cranes with 4-Way Shuttle Racking. This hybrid approach unites the space advantages of high-rise automation with the flexibility of horizontal movement, ensuring continuous, unobstructed inventory flow throughout the facility.
Step 1: Site Survey & Requirements Analysis
At project kick-off, the Everunion team carried out a comprehensive survey of the client's existing warehouse — building structure, available clear height, fire and safety codes, and pharmaceutical zoning requirements — to establish the key constraints the system would need to satisfy, including maximum usable height, floor loading capacity, and fire-zone layout. This provided an accurate foundation for the design that followed.
Step 2: System Design & Engineering Planning
Based on the survey findings, Everunion's design team developed an overall solution built around a 21-meter high-rise AS/RS crane system as the structural backbone, with 7.3-meter-deep 4-way shuttle racking as the core storage unit. The team also planned the location logic for all 11,630 pallet positions, ensuring that different product batches and categories could be clearly zoned and independently managed in line with the client's compliance requirements, while reserving expansion capacity for future business growth.
Step 3: Equipment Manufacturing & System Integration
Once the design was finalized, Everunion coordinated the precision manufacturing and factory testing of key equipment — cranes, shuttles, and racking structural components — under strict quality standards covering structural strength, operating precision, and safety performance. In parallel, the Warehouse Management System (WMS) was integrated and jointly commissioned with the equipment control system, achieving tight coordination between location management, task scheduling, and equipment operation ahead of on-site installation.
Step 4: On-Site Installation, Commissioning & Acceptance
Once equipment arrived on site, the Everunion team completed rack assembly, crane and shuttle installation, control-system commissioning, and both unloaded and loaded operational testing according to the project schedule. This confirmed that all key performance metrics — including retrieval accuracy, operating speed, and safety interlocks — met the design specifications before the system went live, and the team supported the client through final acceptance.
Through this systematic four-stage approach, Everunion translated the client's individual pain points into an executable, verifiable engineering solution — delivering a complete path from requirements to reality.